Roundabout costs 2019/20 - 2021/22

Case reference FOI2022/01682

Published 15 December 2022

Request

This is an information request relating to the cost of roundabout installations. Please include the information for each of the following financial years; 2019/20, 2020/21, 2021/22:

* A list of roundabouts installed by the council including their locations

* The expected budget of each roundabout, when the project was initially begun, and the final cost upon completion

Please only include roundabouts that were completed in these three years and for which figures exist showing the expected budget and the final cost

Response

2019/20 - no roundabouts installed.

2020/21 -

Roundabouts installed:

Lawtons Cross

Weston under Penyard

Expected budget:

Lawtons Cross £315,962.22

Weston under Penyard - £99,179.41

Commencement of works:

Lawtons Cross - April 2020

Weston under Penyard - October 2020

Final cost:

Lawtons Cross - £296,697.13

Weston under Penyard - £98,509.75

2021/22 - no roundabouts installed.

Documents

There are no documents for this release.

This is Herefordshire Council's response to a freedom of information (FOI) or environmental information regulations (EIR) request.

You can browse our other responses or make a new FOI request.