1. Where possible, the amount of miles of dedicated cycle routes in existence in your local authority area on 28/10/2024.
2. Where possible, the amount of miles of cycle routes established in the past 6 years in your local authority area with a breakdown for each calendar year. This time period should include (01/01/2018-01/01/2023) and where possible (01/01/2024-28/10/2024).
3. Where possible, the amount of money spent on cycling infrastructure in the past 6 years in your local authority area with a breakdown for each calendar year. This time period should include (01/01/2018-01/01/2023) and where possible (01/01/2024-28/10/2024).
4. Where possible, the amount of money spent on cycle and scooter share schemes in the past 6 years in your local authority area with a breakdown for each calendar year. This time period should include (01/01/2018-01/01/2023) and where possible (01/01/2024-28/10/2024).
Response
1. Where possible, the amount of miles of dedicated cycle routes in existence in your local authority area on 28/10/2024.
Answer: In terms of the cycle way routes (shared and segregated) there are 39.63 km which is 24.64miles.
2. Where possible, the amount of miles of cycle routes established in the past 6 years in your local authority area with a breakdown for each calendar year. This time period should include (01/01/2018-01/01/2023) and where possible (01/01/2024-28/10/2024).
Answer: This information is not available as we record and maintain the data incrementally. 3. Where possible, the amount of money spent on cycling infrastructure in the past 6 years in your local authority area with a breakdown for each calendar year. This time period should include (01/01/2018-01/01/2023) and where possible (01/01/2024-28/10/2024).
Answer: The majority of the infrastructure is over 15 years old so requires no maintenance intervention. Therefore, we have no maintenance cost for the period. The delivery of new infrastructure in this period has been largely delivered by developers at no cost to Herefordshire Council and therefore we don’t have values for the construction of routes.
4. Where possible, the amount of money spent on cycle and scooter share schemes in the past 6 years in your local authority area with a breakdown for each calendar year. This time period should include (01/01/2018-01/01/2023) and where possible (01/01/2024-28/10/2024).
Answer:
Total: £471,259.51 to September 2024.
2018 £0
2019 £27,289
2020 £63,946.33
2021 £99,295.18
2022 £80,920
2023 £105,226
2024 (up to and including September) £94,583