FOI release

Energy Supply Procurement & Costs

Case reference FOI2022/01578

Published 23 November 2022

Request

For the year ending March 31 2022, please provide your organisation's approximate total annual cost expenditure for grid supplies of:

· Electricity

· Natural gas

Please provide the current total number of supplies (billed meter points) for;

· Half Hourly metered electricity

· Non Half Hourly metered electricity

· Natural gas

The following questions relate to your main supplier or main contracts, I do not require details of suppliers for a small number of miscellaneous supplies)

Please provide the name of your current primary licenced retail suppliers for :

· Half Hourly metered electricity

· Non Half Hourly metered electricity

· Natural gas

Please provide the relevant reference number or similar reference detail of the OJEU framework or tender exercise through which supplies were procured for:

· Half Hourly metered electricity

· Non Half Hourly metered electricity

· Natural gas

If the procurement route is facilitated by a Public Sector Buying Organisation (PBO) (e.g CCS, YPO, etc), please provide the name of the PBO facilitating your contract for:

· Half Hourly metered electricity

· Non Half Hourly metered electricity

· Natural gas

Please provide contact details for the procurement manager at your Organisation responsible for these call-offs or awards of energy supply contracts, or where this person is no longer employed by your Organisation, for the relevant procurement manager currently in post. please provide their:

· Name

· Job Title

· Email Address

Please provide contact details for the operational Manager at your Organisation primarily responsible for day to day management of these supplies & costs. This would usually be an Energy Manager, Estates/Facilities Manager, or similar. Please provide their:

· Name

· Job Title

· Email Address

Response

For the year ending March 31 2022, please provide your organisation's approximate total annual cost expenditure for grid supplies of:

· Electricity

A: £1,136,574

· Natural gas

A: £310,678

Please provide the current total number of supplies (billed meter points) for;

· Half Hourly metered electricity

A: 34

· Non Half Hourly metered electricity

A: 172

· Natural gas

A: 86

The following questions relate to your main supplier or main contracts, I do not require details of suppliers for a small number of miscellaneous supplies)

Please provide the name of your current primary licenced retail suppliers for :

· Half Hourly metered electricity

A: Total Energies Gas & Power Limited

· Non Half Hourly metered electricity

A: Total Energies Gas & Power Limited

· Natural gas

A: Total Energies Gas & Power Limited

Please provide the relevant reference number or similar reference detail of the OJEU framework or tender exercise through which supplies were procured for:

· Half Hourly metered electricity

A: WME002

· Non Half Hourly metered electricity

A: WME002

· natural gas

A: WME001

If the procurement route is facilitated by a Public Sector Buying Organisation (PBO) (e.g CCS, YPO, etc), please provide the name of the PBO facilitating your contract for:

· Half Hourly metered electricity

A: West Mercia Energy

· Non Half Hourly metered electricity

A: West Mercia Energy

· Natural gas

A: West Mercia Energy

Please provide contact details for the procurement manager at your Organisation responsible for these call-offs or awards of energy supply contracts, or where this person is no longer employed by your Organisation, for the relevant procurement manager currently in post. please provide their:

· Name

A: Commercial Services

· Job Title

A: N/A

· Email Address

A: commercialservices@herefordshire.gov.uk

Please provide contact details for the operational Manager at your Organisation primarily responsible for day to day management of these supplies & costs. This would usually be an Energy Manager, Estates/Facilities Manager, or similar. Please provide their:

· Name

A: Danny Lenain

· Job Title

A: Principal Sustainability and Climate Change Officer

· Email Address

A: energy@herefordshire.gov.uk

Documents

There are no documents for this release.

This is Herefordshire Council's response to a freedom of information (FOI) or environmental information regulations (EIR) request.

You can browse our other responses or make a new FOI request.