Replacement and installing costs of the traffic calming humps in Foley Lane
Case reference FOI2025/02086
Received 21 October 2025
Published 13 November 2025
Request
Response
Could you tell me how much the replacement and installing of the traffic calming humps in Foley Lane will be. These humps are due to be replaced on 31 of this month and are due to a drawing error on the councils part.
Answer: The Service Area have advised, the initial costs, which are abortive costs, are for the in-situ construction of the ramps, which was £11,564.00.
Unfortunately, the initial installation was not successful, and the ramps are therefore being replaced with the modular, which cost £23,633.81.
Documents
This is Herefordshire Council's response to a freedom of information (FOI) or environmental information regulations (EIR) request.
You can browse our other responses or make a new FOI request.