FOI release

Approximate average cost for transport projects

Case reference FOI2026/01218

Received 21 May 2026

Published 16 June 2026

Request

Under the Freedom of Information Act, please can you provide the approximate average cost to Herefordshire Council to deliver the following transport projects in the most recent year for which figures are available. For the purpose of this request, please understand approximate cost to mean the total of

i) fees for prelims, traffic management, and signage and road markings),

ii) works contingency,

iii) restricted and night working,

iv) fees for design, project management, construction supervision, and Quantity Surveyor,

v) Traffic Regulation Orders,

vi) Air Quality Assessment,

vii) site investigations,

viii) street lighting assessment, and

ix) Statutory Undertakers Allowance.

1. Installation of Bollard (per bollard)

2. Installation of a Vehicle Activated Sign (VAS) 

3. A Set of Two traffic Speed Cushions   

4. Small Scale Resident Only Parking 

5. Zebra Crossing Single Carriageway, no Splitter Island

Response

Under the Freedom of Information Act, please can you provide the approximate average cost to Herefordshire Council to deliver the following transport projects in the most recent year for which figures are available.

For the purpose of this request, please understand approximate cost to mean the total of i) fees for prelims, traffic management, and signage and road markings), ii) works contingency, iii) restricted and night working, iv) fees for design, project management, construction supervision, and Quantity Surveyor, v) Traffic Regulation Orders, vi) Air Quality Assessment, vii) site investigations, viii) street lighting assessment, and ix) Statutory Undertakers Allowance.

1.      Installation of Bollard (per bollard)

 

A: Costs vary depending on requirements for installation from design, there are a vast number of bollards therefore providing an approximate cost is not possible without a specific request.


2.      Installation of a Vehicle Activated Sign (VAS) 

 

A: Costs vary depending on requirements for installation from design. There are a wide range of VAS available, including a suite of different sizes and purposes. Therefore, providing an approximately cost is not possible based on the information requested.


3.      A Set of Two traffic Speed Cushions   

 

A: The price will vary depending on size, location, material. Therefore, providing an approximate cost is not possible.


4.      Small Scale Resident Only Parking 

 

A: The approximate cost for the Traffic Regulation Order legal work would be in the region of £6,000 to £9,000 depending on the scale and complexity of the scheme. Resident Parking Schemes require a high-level amount of consultation which typically adds to their complexity.


5.      Zebra Crossing Single Carriageway, no Splitter Island

 

A: Cost varies depending on requirements for installation from design. Prices depend on the size and the specific requirements of the site. Therefore, based on this request, it is too broad to provide estimated costs.

 

Documents

There are no documents for this release.

This is Herefordshire Council's response to a freedom of information (FOI) or environmental information regulations (EIR) request.