Cost of Old Mill traffic lights and details of works
Case reference FOI2022/00023
Published 21 January 2022
Request
Could you forward me the cost of hiring the traffic lights at the old mill between Rotherwas and Holme Lacy and an update as to when your contractors / partners Balfour Beatty are going to start the job along with the reason for taking virtually 12 months and No work started.
Response
A. Cost for traffic light hire to 31/12/2021 is £12,145.93
Works are due to commence on site on 5th February with an expected 5 week duration.
Strict environmental regulations due to the nearby watercourse have extended the planning phase of this scheme but now this is in place, we can proceed.