What the Budget was for the drop kerbs work carried out on Harrow Road & Plough Lane in 2022 and the cost of the completed work once it was finished.
Response
What the Budget was for the drop kerbs work carried out on Harrow Road & Plough Lane in 2022 and the cost of the completed work once it was finished
The target cost for the scheme was £54,461.54 including the time covering the scoping and preparation of the works, along with the construction works. There were no changes to the scheme during the works so the out-turn cost remained the same.