FOI release

Roads maintenance Contract

This request was refused in part, so we didn't provide some of the information the requester asked for. This may include information where we can neither confirm nor deny that we hold it.

Case reference FOI2024/00483

Published 26 April 2024

Request

What is the specification the counties roads maintenance contractor has to comply with? What are the terms of there contract excluding any financial information? Does the County have any directly employed road maintenance labour? Please provide an electronic copy of the relevant documents.

Response

What is the specification the counties roads maintenance contractor has to comply with?

A: The Highway Maintenance Plan provides details of the policy and strategy for the council, the current document can be found in the link below, please note this is currently being reviewed and updated.

https://www.herefordshire.gov.uk/downloads/file/5210/highway-maintenance-plan-covid-19

Please find attached Schedule 4 Service Information Annex 0.1, 0.2, 0.3 and 0.4, which is the Base Line Specification for the Contract 4 (which is the Base Line Specification for the Contract) as well as the Pothole Repair Standard Detail.

The Annual Plans published on Herefordshire Council's web site, compliment the Service Information, see link below. Please note the 24/25 Annual Plan will be released in due course.

https://www.herefordshire.gov.uk/council/balfour-beatty-living-places-contract

What are the terms of the contract excluding any financial information?

A: This information is publically available on Herefordshire Council's website and can be viewed via the following link:

https://www.herefordshire.gov.uk/downloads/download/29/balfour_beatty_living_places_contract

As such we consider this information to be exempt under Section 21 of the Freedom of Information Act 2000 because it is reasonably accessible to you via other means. Please take this letter as a refusal notice under S17 of the Act.

Does the County have any directly employed road maintenance labour?

A: Herefordshire Council do not employ people working directly on the network, the service is managed under the Public Realm Contract. However, they do have a small Highways Client team.

Documents

This is Herefordshire Council's response to a freedom of information (FOI) or environmental information regulations (EIR) request.

You can browse our other responses or make a new FOI request.